Construction Staging and 2021 Detours

Year 2020
- Construct embankment along new Dayton Parkway and I-94 ramps
- Construct Brockton Lane (County Rd 101) – minimal traffic impacts
- Construct bridge substructure (abutments and center pier)
-
Year 2021
- Construct bridge superstructure (deck and barriers)
- Reconstruct Dayton Parkway between Holly Lane/Territorial Road and
County Road 81 - Pave I-94 ramps and Dayton Parkway between Brockton Lane (County Road 101) and Holly Lane/Territorial Road
- Activate traffic signals and open all roadways to traffic
Construction Updates
Construction was underway during 2020 for the City of Dayton’s new
I-94/Dayton Parkway Interchange. The project will be completed in 2021. The City of Dayton put together a construction time-lapse video for 2020.
November 2021 Final Construction Update
September 2021 Construction Update
August 2021 Construction Update
April 2021 Construction Update
March 2021 Construction Update
February 2021 Construction Update
January 2021 Construction Update
November 2020 Construction Update
October 2020 Construction Update
September 2020 Construction Update